|
Post Number: 61
|
|
Post Number: 62
|
hymiebravo
Group: Members
Posts: 4989
Joined: Jan. 2006
|
|
Posted on: Aug. 06 2016,11:41 am |
|
|
.....
|
|
|
|
Post Number: 63
|
Self-Banished
Group: Members
Posts: 22480
Joined: Feb. 2006
|
|
Posted on: Aug. 06 2016,12:09 pm |
|
|
^^ prattle on little boy
How's that 12 step thing going?
-------------- Remember boys and girls,
Don’t be a Dick …
Or a “Wayne”
|
|
|
|
Post Number: 64
|
|
Post Number: 65
|
|
Post Number: 66
|
was1
Group: Members
Posts: 1880
Joined: Apr. 2015
|
|
Posted on: Aug. 09 2016,8:57 am |
|
|
The way I see it, the City (specifically the Engineering Department) has failed the residents along this project, at least the ones down in the area of alcitizens. And sadly, the City Council and Mayor do not care and for some reason will not question the City Engineer.
Some of the facts as I understand them - Flooding has been an issue for at least 40 years for this area - City has had this project on their CIP list for roughly 15 years - City has struggled getting this done due to the high costs caused by > poor soils (peat) under the roadway affecting not just the road but also the utilities (water, sanitary and storm) > existing storm system, including lift station and outlet piping are vastly under sized to handle the storm water that gets to this area. over the years other changes have been made to increase the contributing area of storm water to this system sans improvements to the lift station and outlet piping - Alcitizens has tried on MANY occasions to bring up the concern of the storm system and the flooding to the City Engineer, City Council, Mayor, and County Commissioners. None seem to care, understand, or want to do their jobs when it comes to this project and the legitimate concerns and ENGINEERING DESIGN FAILURES that are occurring on this project. - Construction was originally to be completed last fall, nearly a year later and construction still is not done - A construction failure has been identified, the new storm sewer has a sag, a manhole has standing water in it. This was pointed out to the Engineering Department and has not been corrected. Since then the curb and gutter has been installed as well as the first layer of bituminous. So, not only did the Engineering Department not design this project in a way that corrected the known flooding issues, it has allowed a failure to already occur in the storm system and is not going to correct it. So the new storm sewer that has been installed, is not functioning as designed, has reduced the capacity for transporting the storm water and will lead to more flooding issues.
Yes, sometimes Alcitizens maybe does not use the best approach, but I think anyone who has lived through this as he has, has brought up the issues and concerns as many times as he has with no results, is allowed to be frustrated and not be friendly anymore when dealing with the City Officials and Employees who do not care that they have totally messed up this project.
Alcitizens- keep up the fight, keep after the City Engineer, Mayor and Council. REFUSE to pay our assessment until they fix the failed new storm piping and manhole and until they schedule upgrades to the lift station and outlet pipe to eliminate the flooding.
|
|
|
|
Post Number: 67
|
alcitizens
Albert Lea
Group: Members
Posts: 3664
Joined: Jul. 2009
|
|
Posted on: Aug. 18 2016,12:26 am |
|
|
The final 2-inches of asphalt will not be placed until the spring of 2017.
|
|
|
|
Post Number: 68
|
mrugly
Group: Members
Posts: 145
Joined: Jul. 2015
|
|
Posted on: Aug. 18 2016,7:44 am |
|
|
Won't the manhole things be sticking part way up still? If yes how will they plow the street this winter?
-------------- Iowa it stands for Idiots Out Wandering Around! did i just print that?
|
|
|
|
Post Number: 69
|
|
Post Number: 70
|
was1
Group: Members
Posts: 1880
Joined: Apr. 2015
|
|
Posted on: Aug. 18 2016,12:55 pm |
|
|
Typically, the structures (manholes and water valves) are raised to the elevation of the first lift of bituminous and then raised again at the time of the final lift being placed, or just prior to it. I have seen where they bring the manholes and water valves up to the level of what the final pavement will be and then "ramp up" some bituminous around them for the winter. It works but is not the best way of doing this. Can jar the plow drivers, and peoples vehicles.
Will be very interesting to see the settling that occurs on this road the rest of this year, and especially next spring. Hopefully you will keep us posted.
|
|
|
|
|
|